Project · Plastics / Manufacturing

A 30-metre welded stack through the monsoon at Supreme Industries, Jalgaon

ClientSupreme Industries
LocationJalgaon, Maharashtra
Capacity30 m stack
ScopeStructural supply, fabrication and erection of a welded 30 m stack with exhaust piping

The brief

A 2000 kVA Cummins set at Supreme Industries’ Jalgaon plant needed its exhaust taken to full statutory height. Contracted through AG Corporation, the column was specified with welded connections over bolted — better fatigue behaviour, no torque-audit maintenance — and delivered from LOI to final bill in six months, with lifts worked around a running plant.

What made it hard

  • Welded connections specified over bolted — every splice a QA weld, not a torque check
  • Erection sequenced through the 2025 monsoon window
  • A running plastics plant below — crane lifts planned into night and low-activity windows

What we did

  1. 1Structural steel supplied to site and fabricated into the 30 m column
  2. 2Welded lattice stack erected and aligned beside the 2000 kVA set
  3. 3Exhaust piping with expansion bellows and silencer connections completed

From the site

Unretouched photographs from our own site record of this job.

A galvanised lattice stack column held upright by a mobile crane during a night erection
The 30 m column mid-erection at the Jalgaon plant — a night lift, the plant running below.
Night crane erection of a self-supporting lattice chimney tower beside plant buildings
Welding on the splice high above — welded connections were specified over bolted throughout.
Two engineers watching a crane hold a lattice stack section during a night lift
The lift, watched — riggers clear of the load while the section lands.
30 m welded lattice stack
2000 kVA Cummins set served
6 months, LOI to final bill (2025)