Two 1500 kVA turnkey installations at Coca-Cola bottling plants

ClientCoca-Cola bottling plants (Udaipur Beverages & Narmada Drinks)
LocationJabalpur, MP · Bilaspur, CG
Capacity2 × 1500 kVA
ScopeTurnkey installation with synchronising panel and 30 m stack

The brief

Two bottling plants, two 1500 kVA installations. At Jabalpur, the new set had to synchronise with the plant’s existing 1250 and 500 kVA units — three generators of different vintages sharing one bus. At Bilaspur, full turnkey scope including a 30-metre exhaust structure.

What made it hard

  • Cross-vintage synchronisation: a new 1500 kVA set paralleled with existing 1250 and 500 kVA units at Jabalpur
  • Production-line economics — installation sequenced around a running bottling operation
  • 30-metre exhaust structure at Bilaspur, statutory height for the rating

What we did

  1. 11 × 1500 kVA set at Jabalpur with synchronising panel, paralleled to existing sets
  2. 21 × 1500 kVA turnkey installation at Bilaspur with 30 m exhaust structure
  3. 3Commissioning and load testing on both sites

From the site

Unretouched photographs from our own site record of this job.

Raft reinforcement and anchor-bolt cages with base-plate templates for a 30 metre stack foundation
Raft reinforcement and anchor-bolt cages for the 30 m stack foundation at the Bilaspur plant.
2 × 1500 kVA turnkey sets
3-set synchronised bus at Jabalpur
30 m exhaust structure at Bilaspur