Project · Banking & Financial Services

Turnkey 1500 kVA installations for Central Bank of India

ClientCentral Bank of India
LocationKoti, Hyderabad · Belapur, Navi Mumbai
Capacity2 × 1500 kVA
ScopeTurnkey installations with exhaust engineering

The brief

Two premises, two different exhaust problems. Hyderabad took a full 30-metre stack; Belapur required 30 metres of pipeline integrated into an existing exhaust structure — the kind of brownfield engineering that separates installers from contractors.

What made it hard

  • Bank-premises discipline at both sites — access, documentation, audit trail
  • Brownfield exhaust integration at Belapur: new 1500 kVA set into an existing stack via 30 m of engineered pipeline
  • Full-height 30 m stack at Koti, Hyderabad

What we did

  1. 11 × 1500 kVA turnkey installation at Koti, Hyderabad with 30 m exhaust
  2. 21 × 1500 kVA set at Belapur with 30 m pipeline integrated into existing exhaust
  3. 3Commissioning and documentation at bank audit standard

From the site

Unretouched photographs from our own site record of this job.

Completed 30 metre galvanised lattice stack beside a 1500 kVA DG acoustic enclosure
The finished 30 m stack beside the 1500 kVA set at Koti, Hyderabad.
Excavated foundation pit with rebar column cages and brick shuttering
Foundation pit with reinforcement cages and shuttering.
Crane lifting a galvanised lattice stack section over anchor-bolt foundations
First lattice section lifted over the prepared anchor-bolt foundation.
Upper lattice section suspended mid-air being lowered onto the standing base section
Second section landing on the standing base — work at height is splice bolting, not building.
Lattice stack sections in red-oxide primer laid out in the fabrication yard
Sections in red-oxide primer during fabrication.
Twin exhaust risers with flanged expansion bellows rising from a DG enclosure roof
Twin exhaust risers with expansion bellows leaving the enclosure roof — V-engine sets run two lines to one Y-joint.
2 × 1500 kVA turnkey sets
30 m stack + 30 m brownfield pipeline
2 bank premises